Module 3: Project Crashing & Resources
Heuristic Procedures

STEP 3

Holding the last activity fixed, repeat step 2 on the next to the last activity in the network, taking advantage of any slack that may have been made available to it by the rescheduling in step 2.

STEP 4

Continue step 3 until the first activity in the list has been considered. This completes the first rescheduling cycle.