STEP 5
Carry out additional rescheduling cycles by repeating steps 2 through
4 until no further reduction in the total sum of squares of resource
requirements is possible, noting that only movement of an activity
to the right (schedule later) is permissible under this scheme.
STEP 6
If this resource is particularly critical, repeat steps 1 through
5 on a different ordering of the activities, which of course, must
list the activities in order of precedence.
|