Module 3 : Project Crashing & Resources
Heuristic Procedures

STEP 5

Carry out additional rescheduling cycles by repeating steps 2 through 4 until no further reduction in the total sum of squares of resource requirements is possible, noting that only movement of an activity to the right (schedule later) is permissible under this scheme.

STEP 6

If this resource is particularly critical, repeat steps 1 through 5 on a different ordering of the activities, which of course, must list the activities in order of precedence.