| Module 3: Project
Crashing & Resources |
 |
|
Heuristic Procedures |
|
 |
STEP 7
Choose the best schedule of those obtained in steps 5 and 6.
STEP 8
Make final adjustments to the schedule chosen in step 7 taking into
account factors not considered in the basis scheduling procedure.
|
|
| Prof.S.G.Deshmukh & Prof.Arun
Kanda |