List project activities in order
of precedence by arranging the arrow head numbers in ascending order.
When two or more activities have the same head number, list them
so that the arrow tail numbers are also in ascending order. Add
to this list, the duration, the early start and slack values for
each activity.
STEP 2
Starting with the last activity (the one at the bottom of the
diagram), schedule it to give the lowest total sum of squares
of resource requirements for each time unit. If more than one
schedule gives the same total sum of squares, then schedule the
activity as late as possible to get as much slack as possible
in all preceding activities.