Standard PERT Assumptions
- The activities are independent.
- The critical path contains a large no.
of activities so that we can invoke the Central Limit Theorem.
- All activities not on the critical path
are ignored.
- Activity times follow a Beta distribution.
- The mean and variance of the activities
are given by (a+4m+b)/6 and [(b-a)/6]2.
|
|
|