| Module 2 : Project
Planning |
 |
|
PERT Assumptions |
|
 |
CONFIDENCE INTERVALS
- Chances that the project is completed within
- mean +/- 1 sigma 68% (29.41 -- 34.11)
- mean +/- 2 sigma 95% (26.76 -- 36.56)
- mean +/- 3 sigma 99% (24.31 -- 39.01)
|
|
|