Module 2 : Project Planning
PERT Assumptions

CONFIDENCE INTERVALS

  • Chances that the project is completed within
    - mean +/- 1 sigma 68% (29.41 -- 34.11)
    - mean +/- 2 sigma 95% (26.76 -- 36.56)
    - mean +/- 3 sigma 99% (24.31 -- 39.01)
Page 1 - 10
Prof.S.G.Deshmukh & Prof.Arun Kanda