PROBABILITY STATEMENTS

PROBABILITY STATEMENTS

  • Probability of meeting a Target Date,say 36 days.
  • Z (Standard normal deviate) = (36 - 31.66)/2.45 = 4.34/2.45 = 1.77
  • Area from normal tables = 0.9616
  • Probability of exceeding a ceiling, say 28 days
  • Z (Standard normal deviate) =(28 - 31.66)/2.45 = -3.66/2.45 = - 1.49
  • Area from normal tables = 0.0681
  • Probability of duration lying in an interval, say 28 to 36 days
    Area from normal tables = 0.9616 - 0.0681 = 0.8935




Page 1 - 10
Prof.S.G.Deshmukh & Prof.Arun Kanda