Module 2 : Project Planning
AOA and AON Networks

FLOATS Computations : Activity ' f '


- Total Float = LS - ES = LF - EF =3
- Safety float = Total Float - [Max (LF of predecessors)-ES]= 3- (7 -7) = 3
- Free float = Total Float -[LF -Min(ES of successors)]= 3 - (18 - 18) = 3
- Independent float = Total float - both the latter terms= 3 - (0+0) = 3
Page 1 - 10
Page 21 - 26
Prof.S.G.Deshmukh & Prof.Arun Kanda