Module 2 : Project Planning
AOA and AON Networks

FLOATS Computations : Activity 'a'


- Total Float = LS - ES = LF - EF =1
- Safety float = Total Float - [Max (LF of predecessors)-ES]= 1- (0 - 0) = 1
- Free float = Total Float -[LF -Min(ES of successors)]= 1 - (3-2) = 0
- Independent float = Total float - both the latter terms= 1 - (0+1) = 0