Module 2 : Project Planning
AOA and AON Networks

FLOATS Computations : Activity ' c '


- Total Float = LS - ES = LF - EF =9
- Safety float = Total Float - [Max (LF of predecessors)-ES]= 9- (3 -2) = 8
- Free float = Total Float -[LF -Min(ES of successors)]= 9 - (12-12) = 9
- Independent float = Total float - both the latter terms= 9 - (1+0) = 8