Module 2 : Project Planning
PERT Assumptions

PERT Time Estimates


  • Mean of activity duration = (a + 4m + b) / 6

  • Variance of activity duration =
  • Standard deviation of activity duration == (b - a ) / 6
Page 11 - 19