| Module 2 : Project
Planning |
 |
|
Scheduling Probabilistic Activities |
|
 |
Uncertain Activity Durations
- For each activity in the project three time estimates are obtained
- Optimistic time, a
- Most likely time, m
- Pessimistic time, b
|
|
| Prof.S.G.Deshmukh & Prof.Arun
Kanda |