Module 2 : Project Planning
Scheduling Probabilistic Activities

Uncertain Activity Durations


  • For each activity in the project three time estimates are obtained
    - Optimistic time, a
    - Most likely time, m
    - Pessimistic time, b
Page 11 - 19
Prof.S.G.Deshmukh & Prof.Arun Kanda