| Module 2 : Project
Planning |
 |
|
AOA and AON Networks |
|
 |
Early and Late Schedule :
Example
| Job |
Duration |
ES |
EF |
LS |
LF |
TF |
| a |
2 |
0 |
2 |
1 |
3 |
1 |
| b |
3 |
0 |
3 |
0 |
3 |
0 |
| c |
1 |
2 |
3 |
11 |
12 |
9 |
| d |
4 |
3 |
7 |
3 |
7 |
0 |
| e |
5 |
7 |
12 |
7 |
12 |
0 |
| f |
8 |
7 |
15 |
10 |
18 |
3 |
| g |
6 |
12 |
18 |
12 |
18 |
0 |
| h |
4 |
12 |
16 |
14 |
18 |
2 |
| i |
3 |
18 |
21 |
18 |
21 |
0 |
|
|
|
| Prof.S.G.Deshmukh & Prof.Arun
Kanda |