Module 2 : Project Planning
Work Breakdown Structure

FORWARD PASS : AON Networks


Initialization:
  • Early start(ES) for all beginning activities= 0 (or the start date, S for the project)
  • Early finish (EF) for activity = ES+ duration
  • ES(j)= Max (EF all predecessors)
Page 11 - 20
Prof.S.G.Deshmukh & Prof.Arun Kanda