Module 2 : Project Planning
Work Breakdown Structure
FORWARD PASS : AON Networks
Initialization:
Early start(ES) for all beginning activities= 0 (or the start date, S for the project)
Early finish (EF) for activity = ES+ duration
ES(j)= Max (EF all predecessors)