| Module 2 : Project
Planning |
 |
|
AOA and AON Networks |
|
 |
| |
 |
| Path
Enumeration |
| 5 paths |
1
- 2 - 5 - 6 (7)
1 - 2 - 5 - 7 - 8 (12)
1 - 3 - 4 - 5 - 6 (16)
1 - 3 - 4 - 5 - 7 - 8 (21)*
1 - 3 - 4 - 7 - 8 (18)
*Critical path(the longest path) |
|
|
|
| Prof.S.G.Deshmukh & Prof.Arun
Kanda |