Module 2 : Project Planning
Work Breakdown Structure


Example 1

Job Predecessors Duration(days)
a -- 2
b -- 3
c a 1
d a,b 4
e d 5
f d 8
g c,e 6
h c,e 4
i f,g,h 3
Page 11 - 20
Prof.S.G.Deshmukh & Prof.Arun Kanda