Module 2 : Project Planning
Work Breakdown Structure
Example 1
Job
Predecessors
Duration(days)
a
--
2
b
--
3
c
a
1
d
a,b
4
e
d
5
f
d
8
g
c,e
6
h
c,e
4
i
f,g,h
3
1
2
3
4
5
6
7
8
9
10
Prof.S.G.Deshmukh & Prof.Arun Kanda