Concrete pavement construction process
The construction of concrete pavement involves sequential construction of subgrade, sub-base/ base and the concrete slab. These are discussed in the following.
Subgrade preparation
Subgrade preparation involves cleaning, earthwork (excavation or filling of soil, replacement of weak soil, soil stabilization etc.) and compaction.
Where the concrete layer is laid
directly over the subgrade, the subgrade is moist
at the time concrete is placed. If the subgrade is
dry, water could be sprinkled over the surface before
laying any concrete course, however, care should
taken so that soft patches or water pools are not
formed at the surface (IRC:15-2002, Chakroborty
and Das 2003). As an alternative arrangement,
concreting could be done over a water proof polyethylene
sheet, and in that case moistening the subgrade surface
becomes redundant. This polyethylene sheet acts as
a capillary cut-off layer (IRC:15
2002). Figure-31 presents a photograph of subgrade
construction in progress.
Figure-31 Preparation
of subgrade (photo
courtesy: Mr. Pinaki Roychowdhury, Lea Associates
South Asia Pvt. Ltd., New Delhi )
|