Module II : Analysis and design of concrete pavements
Lecture 5 : Design of tie bars
 

Design principle

The tie bars are designed to withstand tensile stresses, the maximum tensile force in the tie bar is made equal to the force required to overcome frictional force between the bottom of the adjoining pavement slab and the soil subgrade. Estimation of spacing and length of tie bar is explained in the following.

Estimation of spacing of tie bar

Since the purpose of the tie bar is to tie concrete slabs together, the area of steel per unit length of longitudinal joint is obtained by equating the total friction to the total tension developed in the tie bar system (as explained in Figure 24).

Figure 24: Estimation of area of steel for tie bar

Thus,

(29)

where μ = co-efficient of friction between concrete slab and the sub-base, W = weight of the concrete slab per unit length (say per meter), σst = allowable working stress in tension for the steel used as tie bar, Ast= cross-sectional area of steel per unit length (say per meter). The weight of concrete slab per unit length can be written as,

(30)

where, w = weight of slab per unit volume (say, cubic meter), B = width of the slab, and h = height of the slab. Thus, from Equation (29) and (30), the area of steel per unit length,

(31)

Assuming suitable diameter of tie bar, the spacing of tie bar can be found out so as to the requirement of steel per unit length.

Estimation of length of tie bar

Consider a single tie bar. The tensile force developed in the tie bar should not exceed the bond strength between the tie bar and the concrete, otherwise it can be pulled out of concrete. Thus, considering one end of the tie bar,

(32)

where, as = cross-sectional area of one tie-bar, P = perimeter of one tie bar, l = length of tie bar inside the concrete slab, Sb = allowable bond strength between the concrete and the tie bar.

Thus, total length of the tie bar, can be written as,

(33)

where z = allowance due to inaccurate centering of the tie bar.