PARETO - OPTIMAL FRONTIER
- The total activity direct cost, Z vs Project duration, T function
is a piecewise linear convex function with progressively non-decreasing
slopes as the project is compressed from the normal to the crash
duration.
- The above feature is found whenever the activity cost - time
trade off is linear.
|