Module 3: Project Crashing & Resources
An Example

PARETO - OPTIMAL FRONTIER
  • The total activity direct cost, Z vs Project duration, T function is a piecewise linear convex function with progressively non-decreasing slopes as the project is compressed from the normal to the crash duration.

  • The above feature is found whenever the activity cost - time trade off is linear.
Pages 11  - 20
Prof.S.G.Deshmukh & Prof.Arun Kanda