| Module 3: Project
Crashing & Resources |
 |
|
An Example |
|
 |
Time and Cost Data
| Activity |
Normal |
Crash |
Cost Slope |
|
Days |
Rs |
Days |
Rs |
Rs/day |
| A |
4 |
100 |
3 |
200 |
100 |
| B |
7 |
280 |
5 |
520 |
120 |
| C |
3 |
50 |
2 |
100 |
50 |
| D |
5 |
200 |
3 |
360 |
80 |
| E |
2 |
160 |
2 |
160 |
INFINITY |
| F |
10 |
230 |
8 |
350 |
60 |
| G |
7 |
200 |
5 |
480 |
140 |
| H |
2 |
100 |
1 |
200 |
100 |
|
|
| Prof.S.G.Deshmukh & Prof.Arun
Kanda |