Module 3: Project Crashing & Resources
An Example

Time and Cost Data


Activity Normal Crash Cost Slope
Days Rs Days Rs Rs/day
A 4 100 3 200 100
B 7 280 5 520 120
C 3 50 2 100 50
D 5 200 3 360 80
E 2 160 2 160 INFINITY
F 10 230 8 350 60
G 7 200 5 480 140
H 2 100 1 200 100
Pages 1 - 10
Page 21 - 28
Prof.S.G.Deshmukh & Prof.Arun Kanda