Flexibility in Activity Durations
- Normal duration entails least activity cost.
- With expenditure of additional resources it is generally
possible to accomplish the activity in a shorter duration.
- The minimum possible duration of the activity is its
crash duration, when its cost is the highest.
- For technological reasons it is not possible to shorten
duration below the crash limit even by spending more money
or resources.
|
|