Module 3: Project Crashing & Resources

Flexibility in Activity Durations
  • Normal duration entails least activity cost.

  • With expenditure of additional resources it is generally possible to accomplish the activity in a shorter duration.

  • The minimum possible duration of the activity is its crash duration, when its cost is the highest.

  • For technological reasons it is not possible to shorten duration below the crash limit even by spending more money or resources.