Module 2 : Project Planning
AOA and AON Networks
Activity Schedule from Event Times
Early start of activity ij = ES(ij) = Ei
FORWARD PASS
Early finish of activity ij= EFij = ES(ij)+ tij
Late finish of activity ij = LF(ij) = Lj
BACKWARD PASS
Late start of activity ij = LS(ij) = LF(ij) -tij