Module 3 : PPP - Procurement Process

Lecture 11 : PPP Contractual Package

4.  CONSTRUCTION AGREEMENT

Lenders are prepared to look primarily to the reserve steam of the BOT facility once it is operating. Construction agreement helps the lender to analyze the risk involved before the start-up of a project (Completion risk & risk mitigation measures). Lenders will look primarily to the project company for cost, schedule and completion guarantees during the construction period. Project company, in turn, will try to reallocate this risk as far as possible to the contractor through construction agreement or where appropriate, into the insurance market.

Investors in the project company are making investment with the intention of directly winning the construction contract/equipment supply contract. Will prefer to avoid competitive bidding and want to negotiate a risk-free contract and taking profit from construction contract. It is also essential that such conflicts are recognised and risks allocated at an early stage in the negotiations between project participants. Project Company may propose a contracting strategy but it is often the requirements of lenders and host government that dictate the procurement strategy and the minimum terms in the contract.

As per the lenders' requirements, the construction contract for the project should be on lump-sum turnkey basis, which ensure that the construction contract is committed to a defined scope of work; to a firm price for the construction works; and to a stipulated time in which to carry out those works. In order to ensure that contractor is not prevented from completing on time and within budget, lenders also seek to limit the project company from changing the scope of work. And, the circumstances in which contractors may claim relief for force majeure should also be limited, clearly defined and coordinated with project agreement. Lenders also wish to confirm that contractor has a proven track record of competency and experience in all areas relevant to the project and financial ability to carry out and complete the works. In addition to the lenders, the requirements of the host governments should also be taken into account in the construction agreement. The construction agreement needs to take into consideration the following issues:

Besides the need to take into consideration the requirements of the host government and protect the interests of the lenders, the other key contractual issues are relating to quality and performance of the project facilities, pricing and payment aspects, and transferring the work to subcontractors. These contractual issues are discussed below.

REFERENCES FOR FURTHER READING ON THE TOPIC

Kerf, M., Gray, R. D., Irwin, T., Levesque, C., and Taylor, R. R. (1998). "Concessions for infrastructure - A guide to their design and award." World Bank Technical Paper No. 399 , World Bank, Washington D.C.

UNIDO. (1996). Guidelines for infrastructure development through Build-Operate-Transfer approach , UNIDO, Vienna.