| Estimation of resources : In order to estimate the resources , the project manager must consider the efficiency of the machine , productivity of labour , learning process , site conditions , impact of weather . For example , person at floor level can do more plastering than standing on the scaffolding . Similarly a person's efficiency is less at the start of the work and increases slowly and reaches the saturation level following the learning curve as shown -
|