- Project Control and project review : The planning is pre-construction activity . The schedule of the project tells the project manager how to arrange the various activities and what resources will be required at a particular instant of time , and how much progress is to be expected . During the construction phase , the schedule serves as the yard-stick to check whether the project may be ahead of plan or behind the plan . If it is behind , then network schedule also helps for further resource mobilization .
|
|