- Draw the bar chart corresponding to the following activity based network.
- Suppose there are overlapping activity on the bar chart. Is it possible to draw corresponding activity based network.
- Consider the following immediate preceding activity table. Draw the network considering activity on the arrow and calculate the earliest start time, the earliest finish time and the latest finish time of each of the activity. Obtain the critical path. Considering early start of the activity. Obtain the resource required at various time
(see next slide).
|
|