Activity Time

In the network, it is important to know the criticality of the activity, time available to perform the activity provided date of completion of a project. In the previous section we have already talked about various method of obtaining activity duration. We shall be interested in the question that

  1. How early we can start the activity.

  2. How much we can delay the activity such that target date of completion of project is not affected

  3. What the time available to perform the activity.

To answer the above question we shall associate (define) following time with an activity

a)       Early start time

b)       Early finish time

c)       Latest start time

d)       Latest finish time