Module 1 : Site Exploration and Geotechnical Investigation
Lecture 2 : Boring Methods of Exploration [ Section 2.1 : Different Types of Boring Methods ]
   
  Disadvantages :
Blind zone effect: If > , then wave refracts more towards normal then the thickness of the strata is neglected.
Error also introduced due to some dissipation of the velocity as longer the path of travel, geophone receives the errorous readings.
 
Error lies in all the assumptions.
2.1.3 Role of geophysical methods in solving geotechnical problems
Gravitational and magnetic methods are used in mining and petroleum engineering. In geotechnical engineering, the gravitational method has very limited use for survey of unconsolidated sediments over the dense bedrock.
 
Magnetic method is applied to locate dikes, faults and buried pipes and other concealed magnetic metal works.
For dam and bridge sites, to locate depth of the solid rock, seismic and resistivity methods are used.
For design of the underwater foundation resistivity method is used.
For building sites to locate hard rock strata/ soft strata seismic method is used.
Slope design and the landslide investigation can be done using seismic and the resistivity methods.
To locate the shallow deposits, seismic and the resistivity methods can be used as in excavation work in sand, gravel deposits etc.
 
Ground water investigation can be done using seismic and resistivity method.
  In the evaluation of insitu concrete, geophysical methods are used to determine uniformity of concrete. detection of cracking, assessment of rate of corrosion etc.
 